The quick answer

Go through every line with your designer. A good Singapore quote splits the job by trade, gives a quantity and unit rate for each line, lists what is excluded, flags any provisional sums, and ties payments to milestones. If a line says "as required" with no breakdown, ask for one before you sign.

Key points

  • Read every line. Understanding it is what lets you make smart trade-offs.
  • Carpentry is usually priced per foot run, tiling and ceilings per square foot, electrical and plumbing per point.
  • A provisional sum (PS) is a placeholder. Ask what's assumed inside it.
  • Ask for exclusions in writing. They tell you more than the total.
  • Pay against milestones, not dates, and never a large deposit upfront.

Why should you read every line?

Yes, it's long. Read it anyway. It isn't only that each line costs money. It's that understanding them lets you have a real conversation.

Sometimes it comes down to whether an extra cabinet is worth more to you than a full-length mirror or a finished ceiling. Maybe you want both. The choice is yours, but you can only make it well once you understand it.

What do the words in a renovation quotation mean?

Term What it means What to ask
Hacking Demolishing existing walls, floor finishes or built-ins to prepare for the new layout Exactly what is being removed, and is disposal included?
Make-good Patching and restoring surfaces after hacking or removal so they're ready for finishing Which surfaces, and to what finish?
Provisional sum (PS) A placeholder price for work not yet finalised. It can move What's assumed inside it, and what would firm it up?
False ceiling A lowered ceiling that hides wiring, pipes or aircon trunking and shapes the lighting How far does it drop, and where?
Carcass The internal box of your carpentry What material, not just which laminate?
Foot run (pfr) Length of carpentry measured along the wall, in feet Does the rate include the countertop and hardware?
Variation order A change to the agreed scope, priced separately How are changes approved?
Resale HDB flat mid-renovation showing a hacked wall, a make-good patch and a false-ceiling frame

What units and rates should you expect?

Rates vary by firm, finish and flat. These ranges come from one Singapore quotation guide published in July 2026 and are only a sense check.

Trade Usual unit Indicative 2026 range
Kitchen cabinets per foot run about $180–$360
Wardrobes per foot run about $200–$360
Tiling per sq ft about $6–$12
Electrical point per point about $45–$90
Plumbing point per point about $120–$300
Painting, glass and aluminium by scope depends on flat size and extent

Note that a carpentry foot-run rate often excludes the countertop. Check whether yours does.

Get a rough number for your own flat in one minute. Try the cost calculator

What is often missing from a quote?

A 2026 Singapore quotation guide lists these as common gaps in headline prices:

  • haulage and debris disposal
  • screeding and waterproofing
  • extra electrical points beyond the count quoted
  • a professional engineer's endorsement where needed (the guide puts it at about $800–$2,000 when masonry walls are hacked)
  • loose furniture, appliances, lighting fixtures and curtains

If they're not in the quote, either add them or put them in your budget buffer.

How should payments be staged?

A 2026 Singapore quotation guide describes 10/40/40/10 as the standard schedule: 10% on signing, 40% after hacking and masonry, 40% after carpentry installation, and 10% at handover, after the defects walkthrough. Release each payment when the milestone is done, not on a calendar date. CaseTrust-accredited renovation firms cap the first deposit at 20% of the total and protect it with a performance bond.

What are the red flags?

  • One lump sum with no quantities.
  • "As required" lines with no breakdown.
  • A total far below other quotes. That's usually missing scope, which returns later as variations.
  • No written contract, validity date or exclusions list.
  • A large deposit before any work starts.
Tape measure along a plywood kitchen cabinet carcass in an HDB kitchen, showing how carpentry is measured by the foot run

How do you compare quotes fairly?

Line them up trade by trade, not by total. Check the same items, quantities and specifications appear in each. A cheaper quote with a particle-board carcass and no haulage is not cheaper than one with plywood and haulage included. Our renovation cost calculator gives you a starting range before you meet anyone.

Questions homeowners ask

What is a provisional sum in a renovation quote?

An allowance for work that isn't fully defined yet. The final cost can be higher or lower. Ask what the figure assumes and when it will be firmed up.

Is "per foot run" the same as per metre?

No. It's measured in feet along the length of the cabinet. One metre is about 3.3 feet, so a 3 m kitchen run is roughly 10 foot run.

Should hacking and make-good be separate lines?

Ideally, yes, with what's being removed and what's being restored stated clearly.

Can I remove items from the quote to save money?

Yes. That's the point of reading every line. A good designer will tell you which cuts you'll regret and which you won't notice.

Who gives clear, itemised renovation quotes in Singapore?

CAsarté Interior is a Singapore design-and-build firm for HDB, condo and landed homes. Our quotes are fixed-price and itemised, we walk you through every line, one project manager runs your job, and our work carries a 1-year workmanship warranty. WhatsApp +65 8902 7516.

Sources

URL Title What it supports Accessed
https://www.smartcalculator.sg/articles/renovation-quotation-guide-singapore-2026 Renovation Quotation Singapore (2026): How to Read and Compare a Quote Trade lines, units, 2026 rate ranges, exclusions, 10/40/40/10 schedule, red flags 2026-11-18
https://case.org.sg/casetrust/casetrust-accreditation-for-renovation-businesses/ CaseTrust Accreditation for Renovation Businesses 20% deposit cap, deposit bond, written variations 2026-11-18
CAsarté Reno Starter Guide (internal) The Truthful, No-BS Reno Starter Guide Definitions of hacking, make-good, PS, false ceiling, carcass 2026-11-18
CAsarté Design is the design team at CAsarté Interior, a Singapore design-and-build studio for HDB, condo and landed homes. We’re homeowners too. How we research and check our guides

Keep reading

Handover check of a soft-close kitchen cabinet with a defects checklist in a newly renovated Singapore condo

Getting started

Renovation warranty in Singapore: what does "lifetime warranty" really cover?

First interior design consultation in a resale 4-room HDB living room with floor plans on the table

Getting started

Questions to ask an interior designer in Singapore (first consultation checklist)

Young couple reviewing a renovation quotation and samples in an empty BTO HDB flat after key collection

Cost & budget

Renovation contingency in Singapore: how much buffer should you keep?