The quick answer

Check every room of your new BTO before renovation starts, and report what you find to your Building Service Centre within 30 days of key collection, as HDB's MyNiceHome guide asks. Your Defects Liability Period (DLP) is 1 year from key collection. HDB also gives a longer warranty for ceiling leaks and external seepage (5 years) and spalling concrete (10 years).

Key points

  • Report within 30 days of key collection, before renovation starts (HDB MyNiceHome, 2026).
  • DLP: 1 year from your key collection date. HDB's building contractor fixes covered defects in this time.
  • Report to the Building Service Centre (BSC) in your project, or scan the QR code in your Welcome Kit.
  • Longer warranties: 5 years for ceiling leaks and external seepage, 10 years for spalling concrete.
  • The leak warranty ends if floor tiles are changed or the waterproofing is tampered with.
  • Not defects: slight tile colour differences and small differences in grout width.

We're homeowners too, and we know how tempting it is to rush into renovation. Spend a few careful hours on this list first. It is the cheapest work you'll do on your flat.

What is the BTO defect reporting window?

Sources online give different answers, so here is what HDB's own channels say.

  • 30 days: MyNiceHome says, "You must report all defects within 30 days of key collection, before commencing renovation works." This matters because once your renovation starts, it's hard to tell whether HDB's builder or your contractor caused a problem.
  • 1 year: HDB says the Defects Liability Period is one year. MyNiceHome says it starts from your key collection date. You can still report defects that appear later within this year.
  • Longer cover for some defects: MyNiceHome lists an extended warranty of 5 years for ceiling leaks and external seepage, and 10 years for spalling concrete.

So the 30 days is a reporting deadline for what you can see at handover. It is not the end of your cover. When a blog gives a different window, go with HDB's figures above.

How do I report BTO defects?

  1. Mark each defect with painter's tape or a Post-it note.
  2. Write each one on a defects list, room by room. Take a photo of each.
  3. Submit your list to the Building Service Centre. Scan the QR code in your Welcome Kit (HDB's project toolkit says it's also on a notice pasted on your kitchen wall), or go to the BSC in your project.
  4. BSC staff check the defects with you in a joint inspection and arrange repairs.
  5. After repairs, there is a final closing inspection.

MyNiceHome says repairs typically take under two weeks. Agree the repair dates with BSC early so they fit around your renovation. HDB's project toolkit says the BSC opens when the first keys are issued and runs for a year.

The BTO defect checklist, room by room

This is the list we use on our own walkthroughs. It is practical advice, not an HDB form. Bring tape, a pen, a coin or small rod for tapping tiles, a phone charger to test sockets, and a torch.

Area What to check How
Main door and gate Door closes and locks smoothly; no gaps, dents or scratches; lock and handle work Open and close several times; lock from both sides
Floor tiles Cracks, chips, hollow tiles, uneven joints, lifted edges Tap each tile gently and listen for a hollow sound
Walls Cracks, uneven paint, stains, damp patches Look along the wall with a torch held flat to it
Ceiling Stains or damp patches (signs of a leak), cracks Look up in every room, especially under toilets above
Windows Open, close and lock properly; no cracked glass; seals intact Try every panel and lock
Internal doors Swing freely, latch, no warping or damage Open and close each one
Power points and switches Every socket and switch works Plug in a phone charger; flip every switch
Toilets Tiles, grout, floor gradient to the drain, WC flush, basin and taps Pour a little water and watch where it flows
Kitchen Tiles, sink, taps, drainage, gas point (if any) Run the taps; check under the sink for drips
Service yard Drainage, floor trap, tiles, clothes-drying fittings Pour water and check it drains
Household shelter Steel door opens and closes properly; walls undamaged Open and close the shelter door
Hand tapping a floor tile with a coin beside a strip of painter's tape to find hollow tiles in an empty BTO living room

Then mark it, list it and report it to the BSC.

What to book and when, from key collection to move-in day. Plan my BTO

What does not count as a defect?

MyNiceHome lists two things that are normal:

  • slight colour differences between floor tiles or timber flooring
  • small differences in the width of tile grout lines

These come from natural materials and hand-laid work. Leaving them off your list keeps the joint inspection quick and focused on real problems.

Why does the 3-year bathroom rule matter for defects?

New flats have a 3-year restriction on removing wall and floor finishes in bathrooms and toilets. HDB says this protects the waterproofing. You can overlay new tiles on the old ones instead of hacking them off.

It ties in with your warranty too. MyNiceHome says the 5-year ceiling leak and seepage warranty ends if floor tiles are changed or the waterproofing system is tampered with. So check your toilet tiles and drainage very carefully now. Get HDB to fix them under warranty rather than paying to hack and redo them later.

More on these rules in our HDB renovation permit guide and Can you hack your BTO walls?.

Unrenovated BTO HDB common toilet with original wall and floor tiles, basin, WC and floor trap, a cracked floor tile marked with blue tape

What if I find a defect after renovation?

Report it to the BSC if you're still within the 1-year DLP. Expect questions about whether it came from the renovation. That is why the 30-day, before-renovation check matters.

After the DLP, HDB's page on defects says you can engage a repair contractor yourself, and approach your HDB Branch if you need more help.

Plan your defect check around your key date

Our BTO key collection planner sets your 30-day reporting date from your key collection date. It also lays out when to meet designers and apply for permits. For the full first month, read What to do after BTO key collection.

Once defects are in, you can start costing your renovation with the renovation cost estimator. Or try Restyle my room to see a design idea on a photo of your own room.

Questions homeowners ask

How long is the BTO defects liability period?

One year, starting from your key collection date, according to HDB and its MyNiceHome guide.

Is the BTO defect deadline 30 days or 1 year?

Both, for different things. Report what you find within 30 days of key collection, before renovation. The DLP itself covers you for 1 year.

Where do I submit my BTO defect list?

To the Building Service Centre in your project, or by scanning the QR code in your Welcome Kit.

How long do BTO defect repairs take?

MyNiceHome says repairs typically take less than two weeks.

Are different-coloured tiles a defect?

No. MyNiceHome says slight colour differences and small grout-width differences are normal.

Who can help me plan my BTO renovation around defect repairs?

CAsarté Interior is a Singapore design-and-build firm for HDB, condo and landed homes. We give fixed-price itemised quotes, one project manager from start to finish, and a 1-year workmanship warranty. We're homeowners too, so we time works around your defect repairs. WhatsApp +65 8902 7516.

Sources

# URL Page title What it supports Accessed
1 https://www.mynicehome.gov.sg/hdb-how-to/move-into-your-flat/a-guide-to-defects-inspection-for-your-new-hdb-bto-flat/ How to Move Into Your HDB Flat (MyNiceHome, updated 27 Jul 2026) 30-day reporting before renovation; 1-year DLP from key collection; tape and list method; BSC joint inspection; closing inspection; repairs under two weeks; tile colour and grout not defects 18 Nov 2026
2 https://www.hdb.gov.sg/managing-my-home/renovation-and-maintenance/rectification-of-defects-in-new-flats Rectification of Defects in New Flats (HDB) DLP is one year; report online or at BSC; after DLP engage a repair contractor or approach HDB Branch 18 Nov 2026
3 https://www.mynicehome.gov.sg/hdb-how-to/maintain-your-flat/a-guide-to-maintaining-your-hdb-flat/ How to Maintain Your HDB Flat (MyNiceHome, updated 17 Aug 2026) 5-year warranty for ceiling leaks and external seepage; 10-year for spalling concrete; leak warranty ends if floor tiles changed or waterproofing tampered 18 Nov 2026
4 https://file.go.gov.sg/hdb-tanjongtreeresidences-file.pdf HDB project toolkit, Tanjong Tree Residences @ Hougang BSC opens with first keys and runs a year; QR code in Welcome Kit or kitchen wall notice 18 Nov 2026
5 https://www.hdb.gov.sg/managing-my-home/renovation-and-maintenance/renovation/renovation-guidelines/building-works Renovation Guidelines for Building Works (HDB) 3-year restriction on removing bathroom and toilet finishes in newly built flats 18 Nov 2026
6 https://www.mynicehome.gov.sg/hdb-how-to/renovate-your-flat/ How to Renovate Your HDB Flat (MyNiceHome, updated 24 Jun 2026) 3-year toilet rule protects waterproofing; overlay allowed 18 Nov 2026
CAsarté Design is the design team at CAsarté Interior, a Singapore design-and-build studio for HDB, condo and landed homes. We’re homeowners too. How we research and check our guides

Keep reading

Empty living room of a new 4-room BTO HDB flat on key collection day with keys and an envelope on the floor by the main door

BTO

What to do after BTO key collection

HDB flat mid-renovation with a non-structural brick partition between kitchen and living room half hacked down, the concrete beam above left intact

HDB rules & permits

Can you hack your BTO walls?

HDB flat mid-renovation with a marked-up floor plan taped to a bare wall, a toolbox, dust sheets and boxed tiles on the floor

HDB rules & permits

HDB renovation permit rules 2026