Reno Tips & Insights / HDB rules & permits
HDB Renovation Permit and Hacking Rules (2026)
The quick answer
In an HDB flat, you need an HDB renovation permit before hacking or altering any wall, removing floor finishes, raising wet-area floors, moving doors, or changing toilet finishes after a new flat's first 3 years. Your contractor must be listed in HDB's Directory of Renovation Contractors (DRC), and they submit the permit application online for you. You, the owner, are responsible for having every permit before work starts.
Key points
- The owner is responsible for getting all HDB renovation permits before works begin.
- Only DRC-listed contractors may renovate an HDB flat, even for works that don't need a permit.
- Your contractor applies online. HDB sends you an SMS when it receives the application.
- Any wall you want to hack down or alter needs a permit first.
- Noisy works (like hacking): Monday to Friday, 9am to 5pm only.
- New flats: toilet finishes stay for 3 years.
- Unauthorised works can mean reinstating your flat to its original condition.
We're homeowners too. Permits sound like paperwork, but they protect your flat, your neighbours and your resale. Here's what you need to know, in plain words.
Who applies for an HDB renovation permit?
Your renovation contractor applies online on your behalf. HDB's page says the contractor submits the flat's floor plan showing the proposed work with the application. MyNiceHome says HDB sends you an SMS when it receives the application, and you can view the approved permit with HDB's "Check Renovation Permit" e-Service.
But the responsibility is yours. MyNiceHome is direct: you are responsible for getting all the HDB renovation permits your flat needs before works begin. HDB's page on renovation says the same: "You are responsible for the renovations in your flat."
Which HDB renovation works need a permit?
These are the works MyNiceHome lists as needing an HDB permit (2026):
| Work | Permit needed? | Notes |
|---|---|---|
| Hacking down or altering any wall | Yes | Layout plans, elevations, sections or details must go with the application |
| Building a new wall | Yes | Same drawings needed |
| Removing existing floor finishes | Yes | |
| Raising floor levels in kitchen, balcony, bathroom or toilet | Yes | |
| Changing door locations | Yes | A new entrance cannot be made through a reinforced concrete wall |
| Replacing a main door on a fire escape route (facing a staircase or lift lobby) | Yes | Door and frame must be half-hour fire-rated with a door closer |
| Replacing toilet floor or wall finishes after the 3-year period | Yes | Before 3 years, removal isn't allowed in new flats |
| Glass shower screen | No HDB approval | The floor slab must not be tampered with |
| Air-conditioner installation | Not if your flat can take the load | Generally flats built after 1 January 1994, or upgraded under MUP or HIP |

HDB also evaluates some works, such as wall demolition, and some works need a Qualified Person (QP) to certify or supervise them. Your contractor should tell you which works in your plan need what.
Which licensed workers do I need?
Some trades need a specific licence on top of the DRC listing:
- Electrical works: an EMA-licensed electrical worker (HDB).
- Air-conditioners: a BCA-trained installer (HDB and MyNiceHome).
- Windows: a BCA-approved window contractor listed in the Directory (MyNiceHome).
- Replacing a WC or basin: a PUB-licensed plumber, with pipes kept connected and the floor slab untouched (Qanvast, 2023).
What is the Directory of Renovation Contractors (DRC)?
It's HDB's list of contractors allowed to renovate HDB flats. HDB's page says the Housing & Development (Renovation Control) Rules 2006 require you to engage only contractors from the DRC. HDB's guide says this applies to all renovation in your flat. It is not limited to permit works.
You can check a contractor with HDB's e-Service for DRC Contractors and BCA Approved Window Contractors. Do this before you sign anything.
What are the HDB renovation working hours?
From MyNiceHome (2026):
| Type of work | Allowed | Not allowed |
|---|---|---|
| General works (e.g. plastering, laying floor screed) | Monday to Saturday, 9am – 6pm | Sundays and public holidays |
| Noisy works (e.g. demolishing walls, removing wall or floor finishes) | Monday to Friday, 9am – 5pm | Weekends, public holidays, and the eve of major public holidays |
MyNiceHome also asks you to get your contractor to give neighbours a heads-up, not hog or block the lifts, and dispose of debris properly.

How long can my HDB renovation take?
MyNiceHome says that once HDB approval is obtained, renovation should be completed within 3 months for new flats and 1 month for existing flats.
Typical project lengths quoted by Qanvast for 2026 are longer than a month for resale flats (8 to 11 weeks, depending on flat size). These are typical whole-project figures from one platform, not HDB rules. Ask your contractor how they will plan the noisy, permit-controlled works so they finish within the permit conditions.
What is the 3-year rule for new HDB bathrooms?
HDB says newly built flats have a 3-year restriction on removing wall and floor finishes in bathrooms and toilets. MyNiceHome explains it protects the waterproofing. You can overlay new tiles over the original ones. After the 3 years, replacing toilet finishes or extending a bathroom needs a permit.
When do the 3 years start? HDB's current pages say "newly built flats" without naming a start date. Qanvast (2023) counts it from the block's TOP, and HDB's earlier building works page (archived copy, April 2025) tied it to "the date of completion of the block". Either way, it is likely to be the block's date, not your key date. Check with HDB or your contractor for your block.
What happens if I renovate without a permit?
The Housing and Development (Renovation Control) Rules treat works done without a required permit, or against HDB's conditions or guidelines, as unauthorised. HDB can require you to remove them and reinstate the flat to its original condition, and can do the works itself and recover the cost from you. Under the Rules, an owner who uses a contractor not registered with HDB, or who fails without reasonable excuse to comply with a reinstatement notice, can be fined up to S$5,000.
It also follows you at resale. HDB's resale terms say the seller must regularise or remove any unauthorised renovation works before resale completion.
What about hacking walls?
Hacking any wall needs a permit. Structural reinforced concrete walls, columns, beams and slabs can't be tampered with. Some non-structural walls can come down with approval. We explain how to tell the difference in Can you hack your BTO walls? If you're buying resale, see what hacking adds to the bill in Resale HDB renovation cost 2026.
Plan your permits early
New BTO? Your permits fit inside your first 30 days. See What to do after BTO key collection and the BTO defect checklist. Our BTO key collection planner puts the dates on a calendar. The renovation cost estimator prices your plan, and Restyle my room shows you a look before you commit.
Questions homeowners ask
Do I need a permit to hack a wall in my HDB flat?
Yes. MyNiceHome says you need a permit from HDB before you hack down or alter any wall.
Who applies for the HDB renovation permit?
Your DRC-listed contractor applies online. You, the owner, are responsible for making sure all permits are in place before work starts.
Can I renovate on Sunday in an HDB flat?
No. General works are Monday to Saturday, 9am to 6pm. Noisy works are Monday to Friday, 9am to 5pm only.
Do I need a permit for a glass shower screen?
No HDB approval is needed, as long as the floor slab isn't tampered with.
Can my contractor not be on the DRC if the work is small?
No. HDB requires a DRC contractor for renovation in your flat, including works that don't need a permit.
Who can help with HDB renovation permits?
CAsarté Interior is a Singapore design-and-build firm for HDB, condo and landed homes. We give fixed-price itemised quotes, one project manager from start to finish, and a 1-year workmanship warranty. We're homeowners too, so we explain each permit before we start. WhatsApp +65 8902 7516.
Sources
| # | URL | Page title | What it supports | Accessed |
|---|---|---|---|---|
| 1 | https://www.mynicehome.gov.sg/hdb-how-to/renovate-your-flat/ | How to Renovate Your HDB Flat (MyNiceHome, updated 24 Jun 2026) | Permit list; owner responsibility; SMS and Check Renovation Permit e-Service; DRC; window contractor; aircon rules; glass screen; working hours; completion times; 3-year toilet rule; neighbours, lifts, debris | 18 Nov 2026 |
| 2 | https://www.hdb.gov.sg/managing-my-home/renovation-and-maintenance/renovation/application-for-a-renovation-permit | Application for a Renovation Permit (HDB) | Contractor submits floor plan with application; HDB evaluates wall demolition; EMA-licensed electrical worker; BCA-trained aircon installer; QP for some works | 18 Nov 2026 |
| 3 | https://www.hdb.gov.sg/managing-my-home/renovation-and-maintenance/renovation/important-information-on-renovations | Important Information on Renovations (HDB) | Owner responsible; Renovation Control Rules 2006 require DRC contractors | 18 Nov 2026 |
| 4 | https://www.hdb.gov.sg/managing-my-home/renovation-and-maintenance/renovation/looking-for-renovation-contractors | Looking for Renovation Contractors (HDB) | e-Service for DRC Contractors and BCA Approved Window Contractors | 18 Nov 2026 |
| 5 | https://www.hdb.gov.sg/managing-my-home/renovation-and-maintenance/renovation/renovation-guidelines/building-works | Renovation Guidelines for Building Works (HDB) | 3-year restriction on bathroom and toilet finishes in newly built flats | 18 Nov 2026 |
| 6 | https://web.archive.org/web/20250404045542/https://www.hdb.gov.sg/cs/infoweb/residential/living-in-an-hdb-flat/renovation/guidelines/building-works | Building Works (HDB renovation guidelines, archived copy of 4 Apr 2025) | 3-year toilet rule counted "from the date of completion of the block" | 20 Nov 2026 |
| 7 | https://sso.agc.gov.sg/SL/HDA1959-R15 | Housing and Development (Renovation Control) Rules (Singapore Statutes Online; text read from a mirror copy, Revised Edition 2010 with amendments to 2025) | Rule 3: registered contractor, fine up to $5,000; Rule 4: unauthorised works, reinstatement notice, fine up to $5,000 for non-compliance | 18 Nov 2026 |
| 8 | https://www.hdb.gov.sg/-/media/managing-my-home/selling-a-flat/process-for-selling-a-flat/option-to-purchase/Resale-Terms--Conditions.pdf | Terms and Conditions of Sale and Purchase of an HDB Resale Flat (HDB) | Clause 9.2: seller must regularise/remove unauthorised works before resale completion | 18 Nov 2026 |
| 9 | https://qanvast.com/sg/articles/questions-every-first-timer-has-about-bto-flat-renovations-answered-3111 | Questions Every First-Timer Has About BTO Flat Renovations, Answered (Qanvast, 9 May 2023) | WC/basin replacement by PUB-licensed plumber; 3-year rule counted from TOP | 18 Nov 2026 |
| 10 | https://qanvast.com/sg/articles/what-are-the-expected-renovation-costs-for-hdb-flats-in-2026-3568 | What are the Expected Renovation Costs for HDB Flats in 2026? (Qanvast, 12 Feb 2026) | Resale renovation durations 8–11 weeks | 18 Nov 2026 |